![]() Whenever you baseline the dates of your plan, make sure you reference this date for clarity in cell C3. As you review and revise the plan on a daily basis the dates in columns E and F may change, but the baseline dates should remain static unless you have agreed to re-baseline the plan with project sponsors. If you are creating your plan for the first time then you can put the same dates into columns E and F respectively. These are the dates that your initial plan stated you would complete each task.